Return to the Downtown Index  Latest views of the Harrison Square area as seen from the Lincoln Tower  Harrison Square construction  Latest rendering of the proposed Courtyard by Marriott Hotel  Parkview Field  Rendering of Condo/Retail Building along Jefferson Boulevard  Project Overview  The partially demolished Centro America Restaurant, hit by a drunk driver

some of the above artist rendered images are provided by the City of Fort Wayne or developers of the project

 

AroundFortWayne.com

Harrison Square Calendar

Daily Listing

 

<< September

October 2007

November  >>

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
      1 2

3

Approval received for property taxes to be used as back-up for financing

4 5 6
7 8

Lincoln Parking lots closed

Temporary lot opens

9 10

Legal Notice that construction will begin soon

11 12 13

14

15      Photos

Construction barricades moved into place

Redevelopment Commission Mtg.

16 17

Lincoln Financial Parking Lots closed

18 19 20
21 22 23 24

25 26 27
28 29 30 31

     
<< September

October 2007

November  >>

 

Daily Listing

  • 3rd - Fort Wayne Mayor Graham Richard and Allen County Commissioner Nelson Peters receive the state's approval for the bond financing.  The meeting was held with Cheryl Musgrave, commissioner of the Department of Local Government Finance.  Return
  • 8th - Lincoln Financial Parking Lot bordered by Douglas Avenue and Harrison and Webster Streets closed.  The temporary parking lot constructed along Baker, Brackenridge, Ewing and Webster Streets opens.  Return
  • 10th - Legal ad in local newspapers announces that construction will begin on the Harrison Square project October 30 and be finished by March 9, 2009.  Return
  • 15th - Weigand Construction begins moving barriers around the old Lincoln Financial Group Parking Lot bordering Harrison, Douglas Avenue and Webster Streets.  Excavation for the ballpark area to begin shortly.  Return
    • Redevelopment Commission meets and approves the following:
      • Resolution 2007-71: HOK - $1.7 million contract to design and engineer the stadium
      • Resolution 2007-72: Schenkel Shultz - hired to design the 900 space parking garage.
      • Resolution 2007-73: Fleming Excavating - Decatur firm, $3.1 million for excavation work on the ballpark area
      • Resolution 2007-74: Dewatering Services - Saranac, Michigan, $386,480 for water removal for construction and the ballpark area.
      • Resolution 2007-75: L.A. Electric - Fort Wayne firm, $592,435 for underground electrical work.  Return
  • 17th - The parking lots bordered by Harrison, Lewis, Webster Streets and Douglas Avenue closed by Lincoln Financial Group as well as the LFG parking lot in the 1200 Block of McClellan Street Return

 

> Return to the Harrison Square Index

 

SafeSurf Rated
Blog - E-mail me! - What's New
Copyright © Stephen L. Parker,  2003 - 2008. All Rights Reserved.
 May not be copied in whole or in part without the expressed written permission of the copyright holder.